Sector: Industrial - Pharmaceutical 

Location: Montréal, Québec

Type of projet: Process water 

Type of water: Industrial Wasterwater 

System Capacity: 898 US gallons/min 

Controlled parameters: pH 

Project Overview: 

  • Effluents generated from pharmaceutical operations required pH neutralization prior to discharge. 
  • The project was part of a new plant that needed to respect regulatory requirements at the beginning of its operations, 
  • The project required a high-capacity system capable of handling variable flow conditions. 
  • Integration of automation and instrumentation was essential to ensure operational reliability. 

Magnor Solution: 

Our solution is a neutralization system with a two-step process including: 

  • Pre-neutralization rectangular tank (144 in. x 72 in. stainless steel tank) 
  • Main neutralization rectangular tank (144 in. x 72 in. stainless steel tank) 
  • Automated injection systems 
  • Agitation systems for proper mixing 
  • Transfer pump Control panel with integrated instrumentation (Allen Bradley) 
  • pH monitoring (three probes)